Posted on: November 21, 2024

[ARCHIVED] City of Milford Enhances Infrastructure with 2024 Streets and Utilities Rehabilitation Project

PRESS RELEASE

FOR IMMEDIATE RELEASE

Milford, DE — The City of Milford is pleased to announce significant progress on the 2024 Streets and Utilities Rehabilitation Project, a major initiative aimed at enhancing the city's infrastructure for improved functionality, efficiency, and accessibility. The comprehensive project involves upgrades to water mains, water services, sewer lines, ADA accessibility improvements, and the repaving of streets once construction is complete.

Project Highlights:

· Water Main and Service Upgrades: To date, the city has replaced or verified over 180 water services, ensuring compliance with EPA standards for lead service line remediation. Additionally, 3,000 linear feet of new water main has been installed to increase system capacity and improve water quality.

· ADA Accessibility Improvements: As part of the project, 24 ADA ramps have been updated to enhance sidewalk accessibility, contributing to Milford’s overall walkability score and ensuring that all residents can enjoy safe, accessible pathways.

· Paving and Road Improvements: More than 800 tons of asphalt have been laid, resulting in 0.76 miles of road repaving. The completed road work includes sections of N Church St, NE 8th St, NW 2nd St, SE 3rd St, Richard St, Caulk Rd, NW 6th St, and West St.

Ongoing Work:

· Water Service Transfer: The contractor is currently working on transferring water services from the old main to the new water main on N Washington St, with completion expected by Friday, November 22, 2024.

· Sewer Main Installation: Sewer main installation on S Church St is on schedule, with completion anticipated by November 28, 2024.

· SE 4th St Construction: Construction on SE 4th St is set to begin in late November to address the deteriorating road in front of Fortunata’s Bakery.

Remaining Work:

The remaining work includes construction on N Washington St, S Washington St, S Church/Maple, and the City Hall parking lot. The city is committed to completing these upgrades with minimal disruption to residents and businesses.

Conclusion:

This project is an essential part of Milford’s ongoing commitment to improving its infrastructure and creating a safer, more efficient, and accessible environment for all residents. The city appreciates the cooperation and patience of the public throughout this important endeavor.

For further information and updates on project timelines, please visit the City of Milford’s website or contact the Public Works Department at (302) 422-1110.